  The appointment involved inspection of the property, preparation of a schedule of dilapidations, and negotiation of the claim to settlement.

 

         Following settlement Roger Hannah & Company Limited were appointed to organise dilapidation works.

 

         The role included:-

 

·         Preparation of a schedule of works and tender documentation.

·         CDM Co-ordinator.

·         Contractor Selection.

·         Contract Administration.

·         Monitoring of the works.